/title production: Deploy new stack
/milestone %Extend archive coverage [Roadmap - Collect]
/labels activity::Deployment
Note This proposes a plan to deploy the new stack in production. Please, drop the unneeded actions from the plan.
production:
- swh-charts: Checkout staging branch, adapt values to reference the new lister and loaders (if any)
- Checkout production branch and merge staging branch (they should be aligned)
- Deploy (push production branch and let argocd do its job)
- scheduler: Connect to toolbox pod & register new scheduler task types (if required)
- Tag grafana with "deployment service=loader- service= environment=staging" [1]
-
Checks
- pod images are pulled correctly
- pods are running without issues (rpc starts, celery workers consume messages, ...)
Dashboard to follow [1]
[1] https://grafana.softwareheritage.org/goto/e-c3EAWIz?orgId=1
Refs.